Design of water and wastewater main replacements are underway in the Forest Hills #8 Subdivision on South Alexander Avenue. The existing water and wastewater lines along South Alexander Avenue were installed in the 1950s and 1960s and are in need of replacement. The water main improvements project consists of 1,400 linear feet of 6-inch water line along the 400-500 block of South Alexander Avenue from East Wheatland Road north to South Forest Lane.   The wastewater main improvements project consists of 1,250 linear feet of 6-inch wastewater main along South Alexander Avenue from East Wheatland Road north to Mauk Branch.

A construction contract was awarded on August 6, 2019, to FM Utilities, LLC.  Work began on September 25, 2019, and is scheduled for completion on March 22, 2020.  The construction cost is $644,047.59.

FY18 Water/Wastewater Improvements at S. Alexander Ave.- Map