Last week, installation of the 60-inch storm pipes and 8-inch sanitary sewer was paused due to utility conflicts which are being resolved.

Next, the contractor will install a portion of the water main to fix one of the conflicts and then move east of Sunset Blvd. to install the storm sewer at that location.

The City will work with AT&T to deconflict their cable which is currently conflicting with the sewer main.