street-circle-bluePROPOSITION B > PROJECT: S CEDAR RIDGE

This project in Proposition B includes the reconstruction of pavement and subsurface utilities along a segment of Cedar Ridge Rd. The three segments, Big Stone Gap to Wheatland, Wheatland, to West Ridge, and West Ridge to Camp Wisdom are being studied to determine where the proposed improvements will be of the highest and best use.

Project Cost Breakdown (by %)

  • Engineering & Design - BOND
  • Engineering & Design - Utilities CIP
  • Construction - Utilities CIP
  • Construction - BOND

Overall Progress

Study
Design 0%
Construction 0%

Start Date

Spring 2022

street-circle-white-grey
Current Project Status

Cooridor Study Underway

Estimated Completion

Winter 2024

Project Milestones

Fall 2018
Winter 2019
Spring 2022

Fall 2018

Voters Approved Bond Election

Winter 2019

Preliminary Project Work Begins

Spring 2022

Corridor Study Started

Project Details
Bond Program Year 2018
Proposition B
Project Name S Cedar Ridge
Project Description Reconstruct pavement and subsurface utilities along Cedar Ridge Rd. along one of the studied segments.
Project Status Corridor Study Underway
Last Modified Date 5/24/2022
Project Schedule (subject to change)
Estimated Design Start Spring 2022
Estimated Design Completion Fall 2022
Estimated Construction Start Winter 2023
Estimated Construction Completion Winter 2024
Estimated Project Cost Breakdown
Pre-Engineering 10% $280,000 – 10% ($180K Bond – 6%; $100K Utilities CIP – 4%)
Construction 90% $2,500,000 – 90% ($1.80M Bond – 65%; $700K Utilities CIP – 25%)
PROJECT TOTAL $2,780,000

Project News Updates