PROPOSITION B > PROJECT: S CEDAR RIDGE
This project in Proposition B includes the reconstruction of pavement and subsurface utilities along a segment of Cedar Ridge Rd. The three segments, Big Stone Gap to Wheatland, Wheatland, to West Ridge, and West Ridge to Camp Wisdom are being studied to determine where the proposed improvements will be of the highest and best use.

Project Cost Breakdown (by %)
- Engineering & Design - BOND
- Engineering & Design - Utilities CIP
- Construction - Utilities CIP
- Construction - BOND
- Engineering & Design - BOND
- Engineering & Design - Utilities CIP
- Construction - Utilities CIP
- Construction - BOND
Start Date
Spring 2022

Current Project Status
Cooridor Study Underway
Estimated Completion
Winter 2024
Project Milestones
Bond Program Year | 2018 |
---|---|
Proposition | B |
Project Name | S Cedar Ridge |
Project Description | Reconstruct pavement and subsurface utilities along Cedar Ridge Rd. along one of the studied segments. |
Project Status | Corridor Study Underway |
Last Modified Date | 5/24/2022 |
Estimated Design Start | Spring 2022 |
---|---|
Estimated Design Completion | Fall 2022 |
Estimated Construction Start | Winter 2023 |
Estimated Construction Completion | Winter 2024 |
Pre-Engineering | 10% | $280,000 – 10% ($180K Bond – 6%; $100K Utilities CIP – 4%) |
---|---|---|
Construction | 90% | $2,500,000 – 90% ($1.80M Bond – 65%; $700K Utilities CIP – 25%) |
PROJECT TOTAL | $2,780,000 |