street-circle-bluePROPOSITION B > PROJECT: DANIELDALE ROAD

This project in Proposition B includes the reconstruction of streets on East Danieldale Road between South Main Street and US 67 (Subgrade Issues).

danieldale-rd-us67

Overall Project Status

Design 30% Complete
Construction 0% Complete

Project Cost Breakdown (by %)

  • Engineering & Design - BOND
  • Engineering & Design - Utilities CIP
  • Construction - Utilities CIP
  • Construction - BOND

$5,033,000

TOTAL COST

Start Date

Spring 2019

street-circle-white-grey
Current Project Status

Design Ongoing

Estimated Completion

Winter 2021

Project Milestones

Fall 2018
Winter 2019

Fall 2018

Voters Approved Bond Election

Winter 2019

Preliminary Project Work Begins

Project Details
Bond Program Year 2018
Proposition B
Project Name Danieldale Road
Project Description Reconstruct street and subsurface utilities to include bike and pedestrian facilities along Danieldale Rd between Main St and US 67
Project Status Preliminary design
Project MAPS Project Plan
Last Modified Date 1/17/2020
Project Schedule (subject to change)
Estimated Design Start Spring 2019
Estimated Design Completion Spring 2020
Estimated Construction Start Fall 2020
Estimated Construction Completion Winter 2021
Estimated Project Cost Breakdown
Engineering & Design 9% $433,000 – 9% ($241K Bond – 5%; $192K Utilities CIP – 4%)
Construction 91% $4,600,000 – 91% ($2.61M Bond – 52%; $1.99M Utilities CIP – 39%)
PROJECT TOTAL 100% $5,033,000

Project News Updates

Bond Update: Danieldale Road Corridor Study

Subsequent to the approval of a design contract for the Danieldale Road Street and Subsurface Utilities Reconstruction from South Main Street to U.S. Highway 67, City Council requested Public Works staff perform a corridor study along Danieldale Road to identify the potential for bike and pedestrian facilities. City consultant Dunaway Associates presented their recommendations for […]

See more...