PROPOSITION A > PROJECT: ROTARY PARKING LOT
Parks & Recreation Proposition A will include the creation, expansion and/or replacement of restroom facilities, Kidsville, splashpad, parking, concession stands, trails, lighting and pavilions at various City parks. This project will add a parking lot to Rotary Park, near Venice Drive.
Start Date
Spring 2019

Current Project Status
COMPLETE
Estimated Completion
Summer 2019
Projected Project Timeline
Project Details
- Bond Program Year
- 2018
- Proposition
- A
- Project Name
- Rotary Parking Lot
- Project Description
- Add parking to Rotary Park, near Venice Drive
- Project Status
- TBD
- Project MAPS
- Coming soon
- Last Modified Date
- 5/31/2019
Project Schedule (subject to change)
- Estimated Design Start
- Spring 2019
- Estimated Design Completion
- Summer 2019
- Estimated Construction Start
- Summer 2019
- Estimated Construction Completion
- Summer 2019
ESTIMATED PROJECT COST BREAKDOWN
- Construction: 100%
- $50,000
- PROJECT TOTAL
- $50,000