Last week, the contractor completed the installation of the 42” storm drain pipe east of Sunset Village Dr. for this traffic control phase and began installing the 8″ water line lowering on Bob Lee Blvd.
This week, the contractor will finish installing the water line lowering and complete the installation of the 60” storm drain pipes for this traffic control phase. They will also continue hauling off material from their staging area.
If they complete the installation of the 60” storm drain pipes, the traffic control will change on Monday. The next traffic control phase will be the closure of the left eastbound lane and with the right and middle lanes serving eastbound traffic.
Stay up-to-date on City activities and projects!
The City Manager provides a weekly update to the Duncanville Mayor and City Council of departmental activities and other significant items of interest.
In the interest of keeping the public better informed, the City is pleased to make those updates available to the citizens.
Weekly Update for Week Ending: Friday, May 7, 2021