Design of water line improvements are underway in the Irwin Keasler Addition. The existing water lines were installed in the 1950s and are 6-inch asbestos cement pipe, except in Bow Creek Court where the lines are 2-inch galvanized pipe. These pipes will be replaced with 8-inch PVC lines. Water main improvements will be designed for Bow Creek Drive from Bow Creek Court to the north end of the Red Bird Lane intersection (630 linear feet), Bow Creek Court (300 linear feet), Bow Creek Drive from Round Top Boulevard to Jellison Boulevard (1,100 linear feet), Dula Circle from Frank Keasler Boulevard to north of Rita Lane (400 linear feet), Ida Vista Court from Jungle Drive to the end of the cul-de-sac (250 linear feet), and Jellison Boulevard from Cedar Ridge Road to Bow Creek Drive (700 linear feet). The improvements are scheduled for construction in summer 2019. The engineer’s estimate of probable cost is $880,000.00.