street-circle-bluePROPOSITION B > PROJECT: DANIELDALE ROAD

This project in Proposition B includes the reconstruction of streets on East Danieldale Road between South Main Street and US 67 (Subgrade Issues).

danieldale-rd-us67

Overall Project Status

Design 0% Complete
Construction 0% Complete

Project Cost Breakdown (by %)

  • Engineering & Design - BOND
  • Engineering & Design - Utilities CIP
  • Construction - Utilities CIP
  • Construction - BOND

$5,033,000

TOTAL COST

Start Date

Spring 2019

street-circle-white-grey
Current Project Status

TBD

Estimated Completion

Winter 2021

Project Milestones

Fall 2018
Winter 2019

Fall 2018

Voters Approved Bond Election

Winter 2019

Preliminary Project Work Begins

Project Details

Bond Program Year
2018
Proposition
B
Project Name
Danieldale Rd
Project Description
Reconstruct street and subsurface utilities along Danieldale Rd between Main St and US-67
Project Status
TBD
Project MAPS
Coming soon
Last Modified Date
5/31/2019

Project Schedule (subject to change)

Estimated Design Start
Spring 2019
Estimated Design Completion
Fall 2019
Estimated Construction Start
Winter 2020
Estimated Construction Completion
Winter 2021

ESTIMATED PROJECT COST BREAKDOWN

Engineering & Design: 9%
$433,000.00 – 9% ($241K Bond – 5%; $192K Utilities CIP – 4%)
Construction: 91%
$4,600,000.00 – 91% ($2.61M Bond – 52%; $1.99M Utilities CIP – 39%)
PROJECT TOTAL
$5,033,000

Project News Updates

See more...