PROPOSITION A > PROJECT: TRAILS

Parks & Recreation Proposition A will include the creation, expansion and/or replacement of restroom facilities, Kidsville, splashpad, parking, concession stands, trails, lighting and pavilions at various City parks. This project will include various on-street and off-street trails throughout the City.

armstrong-park-trails

Overall Project Status

Design 0% Complete
Construction 0% Complete

Project Cost Breakdown (by %)

  • Engineering & Design
  • Construction

$1,500,000

TOTAL COST

Start Date

Summer 2019

tree-white-circle-grey
Current Project Status

Under Design

Estimated Completion

Winter 2021

Project Milestones

Summer 2019
Spring 2020
Fall 2020
Winter 2021
Fall 2018
Winter 2019

Summer 2019

Estimated Design Start

Spring 2020

Estimated Design Completion

Fall 2020

Estimated Construction Start

Winter 2021

Estimated Construction Completion

Fall 2018

Voters Approved Bond Election

Winter 2019

Preliminary Project Work Begins

Project Details

Bond Program Year
2018
Proposition
A
Project Name
Trails
Project Description
Various on-street and off-street trails throughout the City
Project Status
TBD
Project MAPS
Coming soon
Last Modified Date
5/31/2019

Project Schedule (subject to change)

Estimated Design Start
Summer 2019
Estimated Design Completion
Spring 2020
Estimated Construction Start
Fall 2020
Estimated Construction Completion
Winter 2021

ESTIMATED PROJECT COST BREAKDOWN

Engineering & Design: 10%
$150,000
Construction: 90%
$1,350,000
PROJECT TOTAL
$1,500,000