Bond Update: New Fire Station No. 1

In December 2019, Core Construction Services of Texas, Inc., was selected as the Construction Manager at Risk firm to manage the preconstruction phase services and construction phase services to aid with the selection of a design team, management of the design process, preparation of the construction contract, selection of the construction contractor, and management of the construction of the new Fire Station No. 1.

  • Selection of an architectural firm to design new Fire Station No. 1 is ongoing
  • Design contract award is anticipated in March 2020
  • Land acquisition for the new fire station is ongoing

For more information regarding construction of the new Fire Station No. 1 bond project, please contact the Public Works Department at 972-780-5015.

Bond Update: Danieldale Road Corridor Study

Subsequent to the approval of a design contract for the Danieldale Road Street and Subsurface Utilities Reconstruction from South Main Street to U.S. Highway 67, City Council requested Public Works staff perform a corridor study along Danieldale Road to identify the potential for bike and pedestrian facilities.

Danieldale Road Project Location Map

Danieldale Road Project Location Map

City consultant Dunaway Associates presented their recommendations for the Danieldale Road Corridor Study during a City Council workshop held in September 2019:

Final end-state along Danieldale Road Corridor – This is what would be designed/constructed between Main Street and U.S. Highway 67 with future corridor reconstruction work along the corridor to also reflect this design:

  • 4 lanes (two each direction)
  • 12-foot shared used path in north parkway
  • 8-foot sidewalk in south parkway

Interim measure along Danieldale Road – This is what would be installed along the balance of Danieldale Road to tie into the bike lanes along Mountain Creek Parkway in Dallas, to the reconstructed section of Danieldale Road between Main Street and U.S. Highway 67 and the planned four-lane road (with bike lanes) in Desoto:

  • convert outside vehicular lane to a 5-foot bike lane with 6-foot buffer
  • 4 lanes (two each direction) would remain for vehicular traffic
  • 5-foot sidewalks along north and south parkway
Conceptual Interim Measure along Danieldale Road

Conceptual Interim Measure along Danieldale Road

On November 5, 2019, City Council approved the Danieldale Road Corridor Study recommendations to convert Danieldale Road to four vehicular lanes with supporting bike and pedestrian facilities as shown in the above conceptual design.

The final design is scheduled to be complete in June 2020.  For more information regarding the Danieldale Road bond project, please contact the Public Works Department at 972-780-5015. 

Danieldale Road Final Design

Danieldale Road Final Design between Main Street and U.S. Highway 67

Bond Update: North Main Street

The City of Duncanville partnered with Dallas County in May 2019 to perform a preliminary engineering study for the North Main Street/Camp Wisdom Road intersection on a 50-50 cost basis.

N Main St Project Location Map

North Main Street Project Location Map

  • The preliminary study is ongoing with an estimated completion date of Spring 2020
  • The Main Street / Camp Wisdom intersection was submitted in October 2019 for funding as part of the Dallas County 7th Call for Projects
  • 7th Call Projects selected for funding require a 50-50 cost participation
  • Dallas County selection of 7th Call for Projects is anticipated in Spring 2020

For more information regarding the North Main Street bond project, please contact the Public Works Department at 972-780-5015.

FY19 Sidewalk Accessibility Program

As a part of the annual sidewalk accessibility program to ensure compliance with the Americans with Disabilities Act (ADA), improvements are planned for various locations throughout the City to provide sidewalks and ADA ramps to provide a walkable community. This program will provide for 6,250 linear feet of sidewalks and 47 barrier-free ramps at seven (7) project locations. Three areas in Greenstone Estates were completed in FY18. The remainder of the program is being completed as the FY19 program.

FY18 Sidewalk Accessibility Program Locations - Map

FY18 Water/Wastewater Improvements in W. Center Street/Center Ridge Apartments/Center Ridge Dr. Construction Underway

Design of water and wastewater improvements is complete for West Center Street, the Center Ridge Apartment complex, and Center Ridge Drive. Installed in 1979, the existing water lines are 8-inch cast iron pipe and the wastewater lines are clay tile pipe. The project consists of 8-inch water main replacement of approximately 3,100 linear feet of along the current alignment of West Center Street from Cedar Ridge Drive to North Horne Street, approximately 2,800 linear feet along the current alignment of the existing 10-foot water line easement within the Center Ridge Apartment complex, and approximately 400 linear feet along Center Ridge Drive from Cedar Ridge Drive to the Center Ridge Apartment complex. The wastewater improvements consist of approximately 2,500 linear feet of 8-inch wastewater main replacement along the current alignment of the existing six-foot sanitary sewer easement within the Center Ridge Apartment complex.

A construction contract was awarded to Douglas Dailey Construction, LLC, on September 3, 2019.  Construction began on October 28, 2019, and is scheduled to be completed by October 23, 2020.  The construction cost is $2,184,136.00.

FY18 Water/Wastewater Improvements in W. Center Street- Map

FY18 Water and Wastewater Improvements on South Alexander Avenue Construction Underway

Design of water and wastewater main replacements are underway in the Forest Hills #8 Subdivision on South Alexander Avenue. The existing water and wastewater lines along South Alexander Avenue were installed in the 1950s and 1960s and are in need of replacement. The water main improvements project consists of 1,400 linear feet of 6-inch water line along the 400-500 block of South Alexander Avenue from East Wheatland Road north to South Forest Lane.   The wastewater main improvements project consists of 1,250 linear feet of 6-inch wastewater main along South Alexander Avenue from East Wheatland Road north to Mauk Branch.

A construction contract was awarded on August 6, 2019, to FM Utilities, LLC.  Work began on September 25, 2019, and is scheduled for completion on March 22, 2020.  The construction cost is $644,047.59.

FY18 Water/Wastewater Improvements at S. Alexander Ave.- Map

FY18 Water Line Improvements in Greenbriar Estates Phase 1 Construction Underway

Design of water main replacements are underway in the Greenbriar Estates subdivision. Installed in the 1970-1980s era, the existing water mains are in need of replacement. The project consists of 1,750 linear feet of main replacement along High Ridge Drive from Crescent Lane to Meadow Ridge Drive, 2,750 linear feet of main replacement in the 1700-1800 blocks of Green Tree Lane, 3,050 linear feet of main replacement in Greenbriar Lane from Green Tree Lane to Wind Ridge Lane, 1,000 linear feet of main replacement in Knob Hill Drive from South Greenstone Lane to Beaver Creek Drive, and 475 linear feet of main replacement in the 1600 block of Nob Hill Circle. The improvements are scheduled for phased construction over a four-year period. The engineer’s estimate of probable cost for these improvements is $1,805,000.00.

Design for Phase 1 (High Ridge Drive from Crescent Lane to Meadow Ridge Drive) is complete, and a construction contract was awarded to Douglas Dailey Construction, LLC, on August 6, 2019.  Construction began on September 9, 2019, and is scheduled to be completed by May 7, 2019.  The construction cost of Phase 1 is $61,160.00.

Construction of FY18 Water Line Improvements in Greenbriar Estates Locations - Map

FY18 Water Line Improvements in Irwin Keasler Addition Construction Underway

Design of water line improvements are complete in the Irwin Keasler Addition. The water mains are being replaced with 8-inch PVC lines. Water main improvements include Bow Creek Drive from Bow Creek Court to the north end of the Red Bird Lane intersection (630 linear feet), Bow Creek Court (300 linear feet), Bow Creek Drive from Round Top Boulevard to Jellison Boulevard (1,100 linear feet), Dula Circle from Frank Keasler Boulevard to north of Rita Lane (400 linear feet), Ida Vista Court from Jungle Drive to the end of the cul-de-sac (250 linear feet), and Jellison Boulevard from Cedar Ridge Road to Bow Creek Drive (700 linear feet).  The engineer’s estimate of probable cost was $880,000.00.

A construction contract is scheduled for award to Aushill Construction LLC on November 5, 2019, with construction beginning in late 2019.  The construction award is $799,723.00.

FY18 Water Line Improvements at Irwin Keasler Locations - Map

FY18 Streambank Repairs at Ferguson Road Construction Underway

Design is complete for drainage, erosion and paving improvements for Mauk Branch Creek along Ferguson Lane to provide bank stabilization and slope protection. The design also provides for improvements to the adjacent ditch and culvert on the west side of Ferguson Lane to capture any stormwater runoff over Ferguson Lane and the slope. The project limits are from the Ferguson Lane cul-de-sac southward for approximately 300 linear feet.

A construction contract is scheduled for award to Excel 4 Construction LLC on November 5, 2019, with construction beginning in late 2019.  The construction award is $421,554.50.

FY18 Streambank Repairs at Ferguson Road- Map